How to Copy a Dataiku Project

An existing project can make a useful template for a new project so that you don’t have to manually replicate the Flow. How to copy a project depends upon whether you want to:

  • Make a copy on the current instance

  • Make a copy on another instance

Technical Requirements

  • Dataiku user with the Create projects global permission

  • Admin rights on the project you want to copy

Make a Copy on the Current Dataiku Instance

  • From the homepage of the project you want to copy, choose Actions > Duplicate project.

Alternatively:

  • From the Projects page, right-click on the tile of the project you want to copy and choose Duplicate project.

Duplicate Project Options

When duplicating a project:

  • It must have a unique project ID. Dataiku provides a default name and ID, or you can choose your own.

  • You have the option to choose what data is included in the export. Be sure that your connections to any databases use the ${projectKey}_ prefix to ensure that there is no conflict over database tables between the original and duplicated projects.

Make a Copy on Another Dataiku Instance

  • From the homepage of the project you want to copy, choose Actions > Export.

  • Download the project export .zip file.

  • From the user homepage of another instance, choose +New project > Import and select the .zip file.

Alternatively:

  • Use the command-line export and import scripts available on the DSS server:

DATA_DIR/bin/dsscli project-export project_key foo.zip
DATA_DIR/bin/dsscli project-import foo.zip
  • Use dsscli project-export -h for a short help.

Export/Import Project Options

When exporting a project, you have the option to choose what data is included in the export. This can be useful if the bandwidth between the Dataiku instances is slow:

  • Deselect the export of non-input data. Once the project is imported on the second Dataiku instance, rebuild the downstream datasets.

When importing a project:

  • It must have a unique project ID. You’ll be prompted if there is a conflict with an existing project on the instance.

  • The new instance must have connections configured for the imported project to use. Do not create a connection to the same location (e.g. the same database) on the second instance: both projects would then write to the same tables (in SQL, Hive, etc.). The last dataset to be computed would overwrite the other dataset stored in the same table.